Binh Thuan basically ensures the disbursement of public investment capital
Lượt xem: 282

(binhthuan.gov.vn) According to the Provincial People's Committee, the cumulative estimated disbursement of public investment capital as the end of January 2023 under the 2022 plan reaches 96.37% of the assigned plan, basically ensuring the disbursement progress as directed by the Government, Resolution of the Provincial People's Council.

 

Determining that disbursement of public investment capital is one of the key political tasks, the Provincial People's Committee has promptly implemented the central directive documents and issued many documents directing the departments, agencies, localities and investors to accelerate the implementation and disbursement of public investment capital in 2022.

 

In order to ensure the disbursement rate of investment capital from the state budget in 2022 reaching 95 - 100% of the plan assigned by the Prime Minister and disbursing 100% of the provincial budget; the Chairman of the Provincial People's Committee has directed to accelerate the implementation of administrative solutions in performing the local financial and budget tasks in the last months of 2022; which requires departments, agencies and localities to focus on a number of tasks and solutions for the development investment expenditure such as: Assigning the investors, the Project Management Board to expeditiously summarize the documents to complete the payment procedures for the remaining unpaid expenses for the projects that have had decisions approving the finalization of investment capital of completed projects; at the same time, to complete the dossier as soon as the volume is checked and accepted and sent to the State Treasury where the transaction is made to complete payment procedures in order to speed up the disbursement of public investment capital in 2022; avoiding the delay in completing the payment documents for the year to accumulate at the end of the year that affects the verification and approval of the completed project's finalization and avoiding the case of transferring investment capital to the next year for the payment procedures which increases the budget balance. The Chairman of the Provincial People's Committee also has assigned the State Treasury of Binh Thuan to closely coordinate with the investors and the Project Management Board to handle arising problems, shortens the control time to pay in the shortest time for projects that are eligible for disbursement.

 

In 2022, the total allocated capital was 5,594,114 million VND. Accumulation of capital payment from the beginning of the year to the end of the previous month was 4,126,673 million VND, reaching 73.77% of the assigned plan. The estimated accumulated capital payment from the beginning of the year to the end of January 2023 was 5,391,115 million VND, reaching 96.37% of the assigned plan.

 

 

TT Dân

Total Access Statistics
  • Đang truy cập: 1
  • Hôm nay: 1
  • Trong tuần: 1
  • Tháng hiện tại: 1
  • Tổng lượt truy cập: 1
Đăng nhập