Focus on carrying out site clearance for the rest stops on the expressway, Vinh Hao - Phan Thiet section
23/08/2024
Lượt xem: 105
(binhthuan.gov.vn)
On the afternoon of 16/8/2024, Vice Chairman of the Provincial People's
Committee Nguyen Hong Hai chaired a meeting to resolve problems and speed up
the progress of site clearance for 02 rest stops and additional feeder roads on
the expressway, Vinh Hao - Phan Thiet section. Attending the meeting, there
were leaders of relevant departments, agencies and localities.
According
to a the Department of Transport, on the expressway, Vinh Hao - Phan Thiet
section has 12,240.9 m of additional feeder road. In recent times, the People's
Committees of districts have organized propaganda and advocacy; up to now, the
households have agreed to hand over the site in advance to the Contractor for
construction of 10,102 m, the remaining of 2,138.9 m, 18 households have not
agreed to hand over the site.
View
of the meeting
After
listening to the opinions and reports of leaders of relevant departments, agencies
and localities, Vice Chairman of the Provincial People's Committee Nguyen Hong
Hai has requested the People's Committees of districts: Tuy Phong, Bac Binh,
Ham Thuan Bac, Ham Thuan Nam to forcus on implementing solutions to speed up
site clearance of additional feeder roads on the expressway, Vinh Hao - Phan
Thiet section.
For
02 rest stops on the expressway, Vinh Hao - Phan Thiet section, Vice Chairman
of the Provincial People's Committee Nguyen Hong Hai has requested the
Department of Natural Resources and Environment to guide the District People's
Committees of Tuy Phong and Ham Thuan Bac relevant orders and procedures to
carry out compensation and site clearance according to regulations.
Nguyễn Phương