The Inter-district Road project along the main canal through Ham Thuan Bac, Bac
Binh and Tuy Phong was approved by the Provincial People's Committee for the
construction investment project at the Decision No. 1673/QD-UBND dated June 22,
2017 with a total investment cost of 950,018 million VND. In which, the central
support is 850 billion VND, the provincial budget is more than 100 billion VND.
The project aims to
provide water for agricultural production and people's activities; at the same
time, completing traffic infrastructure in Ham Thuan Bac, Bac Binh and Tuy
Phong districts with the road length of 104.25 km, and canal length of 40,068
km.
The Project
Management Board of Investment and Construction of Agricultural and Rural
Development said that the current difficulty of the project is the clearance compensation
for 09 households and 01 organization. Therefore, in order to soon to complete
this project, the Project Management Board of Investment and Construction of
Agriculture and Rural Development proposes the Provincial People's Committee to
consider the support policies for households whose houses are not in the
acquired land area but are affected by the Inter-district Road project along
the main canal through Ham Thuan Bac, Bac Binh and Tuy Phong districts; soon to
issue a decision on the specific land price coefficient of this project, so
that the People's Committee of Bac Binh district can approve the compensation
plan for additional land prices.