Speeding up the construction of the North-South Expressway Project in the East, the section located in the province
23/08/2021
Lượt xem: 177
(binhthuan.gov.vn) In
recent time, the departments, agencies and localities have made great efforts
to speed up the construction of the North-South Expressway Project in the East,
the section located in the province. However, up to now, the implementation
volume is still slow compared to the requirements of the Provincial People's
Committee, especially the work of compensation and site clearance; the relocation
of project technical infrastructure works; handling of the ground embankment
materials.
Therefore, in order
to ensure the progress of the construction of the North-South Expressway
Project in the East, the section located in the province as planned, the
Chairman of the PPC requests the Chairpersons of the People's Committees of the
relevant districts to urgently propagate, persuade the remaining 29 households
to soon to receive compensations and hand over the premises; In case not
complying, the People's Committees of the districts must consolidate the
enforcement documents to ensure the completion of handing over the site to the
project construction contractor. The Chairman of the PPC also requests the
District People's Committees of Ham Thuan Bac, Bac Binh and Ham Thuan Nam to
urgently relocate the telecommunications works; water works; high, medium and
low voltage electrical works in the areas.
The Department of
Transport to urge localities and other departments to speed up the construction
of the North-South Expressway Project in the East, the section located in the
province under the directions of the Provincial People's Committee. The
Provincial Public Security to direct the district polices, where the expressway
pass through, to regularly grasp the situation and ensure security and order
throughout the construction process of the project. Binh Thuan Power Company to
direct the District Electricity Units to coordinate with the District People's
Committees in arranging power cut schedules accordingly, creating the most
favorable conditions for the relocation of electrical technical infrastructure
works, ensuring the progress of handing over the site to the construction
contractors.
The Project
Management Unit No.7 and Thang Long Project Management Unit to organize the
site clearance stakes and handover to the District People's Committees for those
additional frontage roads, the extension of the overpasses DT.711 and DT.718; at
the same time, to direct the Contractor to immediately organize the
construction of utility tunnels so that the People's Committees of the
districts can organize the construction of underground relocation of
electrical, water and telecommunications technical infrastructures crossed by
the expressway.
For the work of
ensuring the ground embankment materials, the Department of Natural Resources
and Environment shall cooperate with the Department of Construction and
Transport to speed up the procedures and processing time of each dossier, each
specific stage for material mines under the direction of the Chairman of the
PPC. The Project Management Unit No.7 and the Contractor shall urgently submit
the exploitation permit application for Ham Can land mine, Ham Thuan Nam
district under the guidance of the Department of Natural Resources and
Environment.
The Department of
Natural Resources and Environment to coordinate with the District People's
Committees of Bac Binh, Ham Thuan Bac and Ham Thuan Nam to conduct the
supplement of the land-use plan, planning as guided by the General Department
of Land for 11 mines that the Project Management Unit No.7 has proposed to
license Contractor under the specific mechanism in Resolution No. 60/NQ-CP
dated 16/6/2021 of the Government, as the basis for settling the land
procedures for mines when licensed.
Nguyễn Phương